How five grid operators answered FERC's large load show cause orders
How five grid operators answered FERC's large load show cause orders
Data center growth has outrun the rules for connecting large loads. On June 18, 2026, the Federal Energy Regulatory Commission (FERC) issued show cause orders to six grid operators. Each order set out five preliminary findings on where that operator's rules appear unjust and unreasonable.
Five of the six ISOs met FERC's November 16 show cause deadline for final responses. SPP has until November 20, after FERC held its proceeding in abeyance in August. FERC has accepted none of the filings yet.
Four ISOs propose the same three remedies: a new study process, a curtailable class of service and rules keeping upgrade costs off existing customers. CAISO passes on the study process, service class and upgrade cost rules to the transmission owners that serve the large loads.
Key takeaways
- PJM would fold four separate studies into one 12-month process, half the time its current Cycle takes. MISO, NYISO and ISO-NE all propose a 90-day large load study.
- Four of the five tariff revisions would take effect between February and March. The services start later, ISO-NE's on June 1, 2028 and MISO's curtailable service on January 1, 2029.
- Four grid operators propose new classes of transmission service, answering FERC's call for a connection the operator can curtail. NYISO sets out four, MISO, PJM and ISO-NE three each.
- MISO, NYISO and ISO-NE would curtail a campus in response to high prices. Since July 2023 the average MISO hub passed its $100/MWh threshold in 246 hours a year, and ISO-NE's Internal Hub passed $250/MWh in 94.
PJM would combine four studies into one 12-month process
PJM proposes the biggest change to interconnection timelines, combining four studies into a single 12-month cluster. The cluster would include generation interconnection, merchant transmission, long-term firm transmission service and large load service. PJM states that its Fast Energization Process would take half the time of its current Cycle process, implying a two-year baseline.
MISO, NYISO and ISO-NE all propose a 90-day study, and in each case the 90 days covers the system impact study alone. ISO-NE's runs from execution of the study agreement, and extends up to 120 days longer where it coordinates with a cluster study. MISO's excludes the model building and deficiency cure either side of it, and its first application deadline is March 1, 2027. NYISO's sits inside two study rounds and a one-year assessment.
NYISO proposes the longest end-to-end timeline, at 18 to 24 months, which NYISO acknowledges is longer than the order contemplated. CAISO files no clock of its own but expects the transmission owners that run its studies to meet FERC's 60 to 90 days.
Four grid operators answer the show cause orders with new transmission service
FERC asked each operator to offer a service for a load willing to be curtailed, and four answered with new classes of transmission service. Each of those classes lets the grid operator switch the load off when the system is tight. In exchange the load connects on terms a firm connection does not carry.
NYISO adds four ways a large load can be treated on the grid, more than any other ISO. They run from full firm withdrawal rights down to a Zero Withdrawal Service Load, served entirely by generators behind its own point of interconnection. MISO, PJM and ISO-NE each set out three, and CAISO proposes an interim interconnection its utilities administer instead.
Only ISO-NE and NYISO require new capacity for firm service
Both ISO-NE and NYISO require firm service requests to pair with new dedicated capacity. NYISO has set out where that capacity must sit. ISO-NE has not, and will settle locational requirements, and the meaning of new capacity, with stakeholders in 2027.
NYISO requires a Partner Resource when a project degrades resource adequacy by more than 25 MW. The resource must sit in the load's Capacity Region, and must connect somewhere other than the load's own point of interconnection. The arrangement runs at least 15 years.
ISO-NE attaches its condition to Firm Contract Demand Service. A generator on the expedited interconnection path does not count toward that capacity, because the path carries no capacity rights.
MISO, PJM and CAISO require no dedicated capacity to connect large loads, per their show cause filings. CAISO states that it does not condition large load interconnection on bringing your own generation. MISO's two pairing tracks, filed separately in August and October, remain optional.
Three grid operators propose a price threshold for curtailment in their show cause filings
The show cause orders also asked each operator to set out when it would curtail large loads and its associated requirements. MISO, NYISO and ISO-NE would use a price threshold as a proxy for system stress. This method would let the grid operator curtail through normal dispatch rather than an emergency procedure.
MISO and NYISO would both set their thresholds to bind before a shortage. MISO's would sit at the first step of scarcity pricing, and NYISO's at the point a transmission constraint is fully used. What they price is the cost of serving the load through expensive hours, rather than an emergency response.
In contrast, PJM would curtail via reliability orders and CAISO would leave the terms to a contract with its utility. PJM's method for issuing reliability orders is still being determined after FERC rejected the majority of its large load interconnection proposal.
All three curtailment plans would use the price at the load's own node, with a capped demand bid to enforce the threshold. MISO would interrupt above $100/MWh under its Grid Responsive Integration Transmission Service, in the Day-Ahead and Real-Time markets. NYISO would cap a non-firm load's bid at $200/MWh. ISO-NE would re-dispatch above a $250/MWh Large Load Re-Dispatch Price, two and a half times MISO's level.
These curtailment periods would have a substantial impact on the operations of large loads across the three ISOs. Based on Real-Time prices since July 2023, the average MISO hub spent 246 hours a year above $100/MWh, 2.8% of the time. The average NYISO zone spent 164 hours above $200/MWh, and ISO-NE's Internal Hub 94 above $250/MWh.
Two thirds of MISO's curtailable events last four hours or less
On-site generation, especially natural gas and co-located BESS, has been proposed as a solution during curtailment hours. Both respond quickly enough to serve a load that can be ordered off at short notice. Whether they can hold a campus at full output depends on how long the curtailment lasts.
Since July 2023, two thirds of the average MISO hub's hours above $100/MWh have come in stretches of four hours or less. NYISO's stretches run longer even though they occur in fewer total hours than MISO's. Only 38% of hours at the average NYISO zone appear in stretches of four hours or less, and 14% last longer than a day. ISO-NE sits between the two at 55%.
The length of these windows makes on-site storage a potential means of maintaining output through curtailment in all three ISOs.
The show cause revisions take effect in February and March, pending FERC approval
Four of the five ISOs want their revisions in force between February 1 and March 16. FERC has approved none of them. If FERC does not rule by then, the revisions take effect by operation of law. FERC can also suspend a filing and set it for hearing, which would leave the terms unsettled well past the dates each operator asked for.
ISO-NE is the exception. It asked for November 14, the day after it filed, and for the Commission to waive the 60 days' notice that normally applies.
The comment windows close first, between December 4 and January 15. Those comments build the record for the Commission's decision, and mark the first point at which these revisions could change.
Modo Energy will continue to track the show cause filings through FERC's review, any additional revisions, and the final accepted large load rules.