Poland Battery Buildout Report: 475 MW added in 2026, 1.5 GW due in 2027

Written by:

Poland Battery Buildout Report: 475 MW added in 2026, 1.5 GW due in 2027

Poland added 475 MW of batteries of 10 MW or more in 2026, almost twenty times the 24 MW it had in January, taking the fleet to 499 MW by November. Two Greenvolt-developed 200 MW projects, Ełk and Turośń Kościelna, supplied 400 MW of the additions.

Owners have announced about 1.5 GW of commissioning dates for 2027, and Modo Energy tracks 12.3 GW of projects in total. Projects that already operate, are under construction or hold capacity contracts add up to 11.1 GW, but Modo Energy’s October forecast expects 8.1 GW to be installed by 2030, which implies that about 3 GW of that contracted capacity is delayed beyond 2030 or not built. Only the 24 MW Nowe Czarnowo I has confirmed reserve qualification, and announced tolls and floors cover 0.9 GW of the pipeline.

Key takeaways

  • ​Poland added 475 MW of batteries of 10 MW or more in 2026, taking the fleet to 499 MW. Ełk and Turośń supplied 400 MW.
  • About 1.5 GW of installed capacity is due in 2027, led by Greenvolt’s 600 MW Siedlce. Modo Energy forecasts 8.1 GW by 2030.
  • Only Nowe Czarnowo I (24 MW) has confirmed PSE reserve qualification, after about ten months.
  • 2026 deals cover about 1.7 GW, led by ENGIE, but tolls and floors cover only 0.9 GW of the 12.2 GW pipeline.

Two 200 MW projects drove Poland's battery growth in 2026

Ełk and Turośń Kościelna, each 200 MW / 800 MWh, connected to the grid in June and July. Their scale sets Poland's early buildout apart from Germany, where 91% of Germany's operating battery fleet sits on distribution grids. German connection approvals average 14 MW at distribution level, against 385 MW at transmission level, according to the regulator BNetzA's latest survey.

Before Ełk and Turośń, Energix's 24 MW Nowe Czarnowo I began operating in December 2025, followed by EDF power solutions' 50 MW Stary Grodków in May 2026. Energix has since energised its 25 MW Nowe Czarnowo II, which is now in qualification. Smaller units, such as NGEN's 9.4 MW Łozienica and R.Power's 5 MW Herby, fall below the 10 MW threshold.

Polskie Sieci Elektroenergetyczne (PSE), the transmission system operator, published its first battery count in late October 2026. It reported 1.3 GW and 3 GWh as of 1 October, with no breakdown by segment. Separately, Agencja Rynku Energii (ARE), the state energy market agency, reported 795 MW of batteries rated at 50 kW or less at the end of June, almost all in households. It counted a further 63 MW between 50 kW and 10 MW. Although the reporting dates differ, these figures are broadly consistent with a grid-scale fleet of around 0.5 GW.

Around 1.5 GW is scheduled for 2027, led by Siedlce

Siedlce accounts for 600 MW, about 40%, of the capacity scheduled for 2027. Across the whole pipeline, 2.6 GW is under construction.

The chart below covers projects of 20 MW or more with announced commissioning dates. Sources include owners' announcements, licence and grant decisions, and capacity-market results from URE and PSE.

Sign up to read this article for free

Unlimited access to our free articles

Monthly access to 2 Global Research articles

Benchmarks, Forecasts, Ko and more

Sign up for free

Already have an account? Log in

Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

Copyright© 2026 Modo Energy. All rights reserved