Can US BESS developers risk losing the tax credit over FEOC rules?

Written by:

Can US BESS developers risk losing the tax credit over FEOC rules?

The investment tax credit (ITC) is worth 30% to 50% of the cost of a US battery energy storage project that starts construction through 2033. Since January 2026, the foreign entity of concern (FEOC) rules have denied that credit to projects that rely on Chinese-owned suppliers. China supplied 59% of US lithium-ion battery imports in 2025, so keeping the credit means changing suppliers and paying more.

A US-made battery system can cost $100/kWh more than one supplied from China, although prices vary by supplier. At the median US project cost, a 30% credit covers up to $125/kWh of extra cost. On those figures, the credit is worth more than the saving from a Chinese-owned supplier.

Looking forward, the rules require a rising share of equipment cost to come from suppliers outside Chinese ownership or control. It is 55% for projects that start construction in 2026, 60% in 2027 and 75% in 2030. Only 7 of the 12 North American BESS battery plants reviewed clearly meet the rules today, and three Korean makers own or part-own all 7.


Key takeaways

  • A 30% tax credit covers up to $125/kWh of extra equipment cost, more than the $100/kWh that US-made batteries add.
  • Cells are 52% of equipment cost, so a project with Chinese-owned cells cannot reach the 60% non-FEOC share needed for a 2027 start.
  • The required share rises to 75% for a 2030 start, so developers without a supply contract face higher prices or a lost credit.
  • Announced North American non-FEOC cell capacity reaches 100 GWh by the end of 2027, and up to 135 GWh if pending guidance clears four more plants.
  • Only 7 of 12 North American BESS battery plants are clearly non-FEOC, and Korean makers own or part-own all 7.

A 30% tax credit covers $125/kWh of extra cost

Modo Energy’s Capex survey puts the median total Capex of a US four-hour battery project at $309/kWh. That median covers five projects, some of which already bought US-made equipment. The tax credit applies to all of that cost except grid connection, which the survey puts at $18/kWh.

Buying non-FEOC equipment raises that cost. A US-made battery system costs $215/kWh, against $115/kWh for one supplied from China (before US tariffs on Chinese cells). That $100/kWh difference takes the project to $409/kWh.

The credit more than covers the difference. At 30%, it brings the project down to $292/kWh, below the $309/kWh project with Chinese-owned supply and no credit. The extra cost could reach $125/kWh, or 40% of total Capex, before the credit stopped covering it. With the 10% ITC adder for domestic content, that limit rises to $194/kWh.

Modo Energy's revenue forecast for 2027 to 2046 shows how FEOC supply choices change returns across the project lifetime. At the median cost, in six US markets, the non-FEOC battery comes out 0.5 to 0.8 points ahead.


The non-FEOC share rises from 60% to 75% by 2030

A supplier's ownership decides whether it is a FEOC, no matter where its factories are. The One Big Beautiful Bill Act (OBBBA) calls these suppliers Prohibited Foreign Entities (PFEs). It adopts an existing federal list of six Chinese battery makers, including CATL and BYD. Any other company based in China, or majority owned from China, is a FEOC as well.

The OBBBA also reaches suppliers tied to those companies. A supplier counts as a FEOC if one of them owns 25% or more of its shares. A license for their technology, signed or changed since July 4, 2025, has the same effect.

However, a project does not have to avoid FEOC suppliers entirely. It needs a minimum share of its equipment cost to come from suppliers that are not FEOCs, set by the year construction starts. That share is 55% for a 2026 start and rises 5 points a year, to 75% for a 2030 start.

The credit is all or nothing, so a project that falls short of that share by any margin receives none.

Projects can apply the equipment test with a cost table published by the Internal Revenue Service, which assigns each battery component a share of equipment cost. Cells have the largest share, at 52%. A project with Chinese-owned cells can therefore reach 48% of equipment cost at most under that table, short of the 60% needed for 2027 construction. The Treasury Department's replacement tables are due by December 31, 2026 and could change those shares.


100 GWh of North American non-FEOC capacity is largely sold

Non-FEOC cells are therefore the equipment a project has to secure, and two Korean makers plan most of the North American supply. LG Energy Solution plans more than 70 GWh of energy storage cell capacity there by the end of 2027. Samsung SDI is targeting 30 GWh in Indiana by the end of 2026. At the end of 2025, all US makers together had 20 GWh.

That manufacturing capacity exceeds the BESS forecast to come online. Modo Energy’s forecasts put new BESS in the seven US ISOs at 58 GWh in 2027 and 90 GWh in 2028. Utilities in the Southeast and the West, which sit outside those markets, add to that demand.

However, little of that capacity is open to new buyers. Both makers say their output is committed through 2028. Samsung SDI reported on October 29, 2026 that orders fill its US and Korean plants, and LG said most of its volume is contracted. A developer without a supply contract today is left competing for the remainder or importing non-FEOC cells.


Only 7 of 12 North American plants are clearly non-FEOC

The manufacturing capacity is relatively concentrated. Modo Energy reviewed 12 operating or anticipated North American plants that make battery cells or modules for BESS projects. Of those, 7 are clearly non-FEOC, and a Korean maker owns or part-owns all 7. LG Energy Solution has a stake in 5 of them, alongside Samsung SDI and SK On with 1 each.

Of the other 5 plants, Hithium's in Texas belongs to one of the six listed makers and 4 are waiting on guidance. Tesla, Fixx Energy, Ford and American Battery Factory are majority US-owned. Each has a tie to a Chinese-owned company through equipment, a technology partner, a license or a pilot line. The Treasury Department has not yet said whether those ties make a supplier a FEOC.


The credit pays today, but qualifying gets harder through 2030

The tax credit is worth more than the extra cost of non-FEOC equipment today. At the median US project cost, a 30% credit covers extra cost of up to $125/kWh, or 40% of total Capex. That is above the $100/kWh that US-made equipment adds.

The year construction begins decides how much non-FEOC equipment a project needs. A 2027 start keeps the 60% share even if the project is finished in 2029, while a 2030 start needs 75%.

The risk of losing the credit therefore grows with each start year. The required share rises 5 points a year, while most North American non-FEOC cell capacity is contracted through 2028. Unless more capacity is announced, fewer projects will qualify and non-FEOC equipment will cost more.