Log inSign up
Just now

PJM Buildout Q3 2026: 9.6 GW of BESS projected by 2031, with up to 14.5 GW more from Cycle 1

Written by:

PJM Buildout Q3 2026: 9.6 GW of BESS projected by 2031, with up to 14.5 GW more from Cycle 1

PJM has four cohorts of projects seeking interconnection: the legacy serial queue, Transition Cycle 1 (TC1), Transition Cycle 2 (TC2), and Cycle 1. Across them, 960 projects are targeting full commercial operation in the coming five years. They total 191.5 GW, but less than half will be built.

From the first three cohorts, 55.3 GW is projected to come online by the end of 2031, assuming TC1's pass rate holds for TC2. Two-thirds of that capacity already has signed interconnection agreements. Cycle 1 projects, still in their first phase of studies, could add up to 38.3 GW more at the same pass rate.

BESS accounts for 9.6 GW of the projection, 4.6 GW of which has signed agreements, and Cycle 1 could add up to 14.5 GW more.

Key takeaways

  • Of the 55.3 GW projected online by the end of 2031, 37.7 GW already has signed interconnection agreements. The other 17.6 GW comes from TC2 projects still in study, held at TC1's pass rate.
  • Cycle 1 could contribute up to an additional 38.3 GW, all in 2029-31. Gas and BESS make up 86% of that upper bound.
  • 9.6 GW of BESS is projected online by 2031, and 4.6 GW of that has signed agreements. Cycle 1 could add up to 14.5 GW more.
  • The mix of annual additions shifts from solar to BESS to gas. Solar leads through 2028 and makes up 29.2 GW of the 55.3 GW projected. Including potential Cycle 1 additions, BESS leads in 2029 and 2030, and gas leads in 2031.
  • The projection averages 10.9 GW a year over 2027-31, twice PJM's 2017-25 average of 5.5 GW. Since 2017, PJM has added over 10 GW in only one year: 13 GW in 2018.

55 GW of studied capacity is projected online by 2031, and Cycle 1 could bring an additional 38 GW

Projects with signed interconnection agreements make up nearly all of the 2027 additions. TC2 projects still in study arrive from 2028, lifting the queue-derived build list to a peak of 13.4 GW a year in 2028 and 2029. Additions then taper as the transition-cycle backlog clears.

Cycle 1, which is scheduled to sign its final interconnection agreements by July 2028, fills in as transition-cycle additions decline. Given typical build times after signing, only BESS and solar can come online in 2029, so most of its potential additions land in 2030 and 2031. At its upper bound, set by TC1's pass rate, Cycle 1 would lift 2030 additions from 9.1 GW to an unprecedented 26.8 GW.

The mix of annual additions shifts from solar to BESS to gas. Solar makes up 16 GW of the 24.2 GW projected for 2027 and 2028. Including Cycle 1, BESS is the largest technology in 2029 and 2030, at up to 7.8 GW and 9.7 GW. In 2031, gas makes up 16.7 GW of a possible 23.7 GW, most of it combined-cycle capacity from Cycle 1.

​

AEP and Dominion host over half of the buildout

AEP hosts 14.5 GW of the 55.3 GW projected and Dominion hosts 14.1 GW, together 52% of the total. ComEd is a distant third at 8.6 GW. Cycle 1 is similarly concentrated, with 23% of its upper bound in AEP and 20% in Dominion.

The buildouts in the two leading zones have different technology mixes. AEP is mostly solar, at 78% of its projected new capacity. Dominion is more balanced: solar is 44%, while gas, BESS, and offshore wind from are each a fifth.

Sign up to read this article for free

Unlimited access to our free articles

Monthly access to 2 Global Research articles

Benchmarks, Forecasts, Ko and more

Sign up for free

Already have an account? Log in

Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

Copyright© 2026 Modo Energy. All rights reserved