Italy: Enel leads 16 GWh MACSE as premiums fall
Italy's second MACSE auction secured 16 GWh for delivery in 2029, 60% more than the first. The weighted average premium fell 12% to €11,382/MWh-year.
The larger auction still absorbed only part of a substantial pipeline. Around 67 GWh qualified and 43 GWh was offered, leaving approximately 27 GWh of submitted capacity without an award.
Key takeaways
- Two utilities won most of the capacity. Enel took 69% and A2A 16%, mostly through large projects.
- Regional premiums converged. Area averages now sit within €900/MWh-year, and the island premium seen in round one has disappeared.
- Long-duration batteries won again. Winning projects provide 5.7 to 8 hours of storage, with no four-hour project among the awards.
South and Calabria took 60% of awarded MACSE capacity
South and Calabria received 9.6 GWh, the largest allocation across the four auction areas.
Sicily secured around 3 GWh, roughly six times its first-round award.
Centre-South neared its ceiling, while Sardinia stayed near its floor
Centre-South received 2.8 GWh, close to its ceiling, while Sardinia received 0.53 GWh, just above its minimum.