PJM is on track to serve over 1,000 data centers by 2030

Written by:

PJM is on track to serve over 1,000 data centers by 2030

Key takeaways

  • Modo now tracks more than 2,000 data center facilities nationwide. This includes over 1,200 planned or operating sites in PJM, concentrated among the Dominion (DOM), AEP, ComEd, and PPL utilities.
  • Just four utilities (and their four PJM zones: DOM, AEP, ComEd, and PPL), represent 84% of the load PJM's data center forecast through 2030.
  • 8.2 GW of data centers were already operating across PJM in 2025, and utilities have another 41 GW under contract or construction.
  • Utilities have included another 71 GW in their forecasts that sits somewhere between engineering review and the earliest inquiry stage. The concentrated nature of this buildout means that tracking utilities will show the data center buildout before PJM-level statistics.

Modo Energy · Ko

Where is PJM data center load concentrating, and how fast?

Ask Ko about PJM data center clusters, large-load growth and where it concentrates, and get cited, data-backed answers in seconds. Free to try.

Ask Ko →

Data centers in PJM are highly clustered.

    Sign up to read this article for free

    Unlimited access to our free articles

    Monthly access to 3 Global Research articles

    Benchmarks, Forecasts, Ko and more

    Sign up for free

    Already have an account? Log in

    Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

    Copyright© 2026 Modo Energy. All rights reserved