ISONE's queue is expected to add 2.1 GW from 2027 to 2029, mostly energy storage in Massachusetts

Written by:

ISONE's queue is expected to add 2.1 GW from 2027 to 2029, mostly energy storage in Massachusetts

Modo Energy expects projects in the ISONE interconnection queue to add 2.1 GW of generation from 2027 to 2029, based on historical completion rates. Energy storage leads with 1.65 GW, or 79% of the total, and solar supplies nearly all of the other 0.43 GW. The 1.65 GW of new batteries would take the operating ISONE battery fleet from 0.86 GW to about 2.5 GW.

The 1.65 GW comes from seven battery projects, all with executed interconnection agreements, and six of them are in Massachusetts. Batteries are also all five projects (1.34 GW) still in the ISONE transitional cluster study, the first study under its new cluster process.

The other 0.43 GW is eight solar projects, six of them in Maine, and all eight also hold executed agreements. Another 1.77 GW has a 2026 operation date, led by two offshore wind projects (1.5 GW) that reached full commercial operation this fall. In total, 3.85 GW of the 9.2 GW of live generation requests in the ISONE queue, across all technologies, is expected online from 2026 to 2029.

The five cluster study batteries could still withdraw. 13 of the study's 18 first-time projects had withdrawn as of October 29, six of them within a week of ISONE's October 20 deadline to execute agreements. Deposits of 20% of each project's network upgrade costs fell due on October 30 or after November 4, and we have no data after October 29 on whether the five paid.

Key takeaways

  • Batteries account for 79% of the 2.1 GW of new generation expected online in ISONE from 2027 to 2029.
  • Massachusetts hosts 1.5 GW of the 1.65 GW of new batteries, including 1.3 GW in Boston.
  • Solar adds 0.42 GW from 2027 to 2029, mostly in Maine, and natural gas adds only 75 MW of upgrades to existing plants in 2026.
  • All five projects left in the ISONE transitional cluster study are Massachusetts batteries, totaling 1.34 GW.
  • The 2029 forecast excludes three offshore wind projects totaling 3.2 GW that hold interconnection agreements but no signed power contracts.

Batteries are 79% of ISONE additions, mostly in Massachusetts

Of the seven battery projects expected online by 2029, six are in Massachusetts (1,511 MW) and one is in Connecticut (142 MW). Boston alone has 1,262 MW.

Sign up to read this article for free

Unlimited access to our free articles

Monthly access to 2 Global Research articles

Benchmarks, Forecasts, Ko and more

Sign up for free

Already have an account? Log in

Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

Copyright© 2026 Modo Energy. All rights reserved