Augmentation and staging: how to approach expanding BESS projects in the NEM

Written by:

Augmentation and staging: how to approach expanding BESS projects in the NEM

Developers in the NEM are expanding battery projects through augmentation and additional stages, with a growing focus on extending duration. Falling battery costs, improving energy density and changing revenue dynamics are driving these decisions.

Existing battery sites and grid connections are valuable assets amid longer connection queues and planning bottlenecks, even if they are degraded or have seen revenues decline. For batteries operating over 15–20 years, the flexibility to expand capacity and adapt to changing market conditions can create long-term value.

Owners can increase power or energy capacity by augmenting an existing battery or adding a separate project stage. More power raises output, whilst more energy extends discharge duration or restores capacity lost through degradation.

Owners can also retrofit existing renewable generation, combining batteries with solar or wind behind a shared grid connection.


Executive summary

  • Staging is common in the NEM, with several projects building modules over multiple years and extending overall duration. Hornsdale is the only example of augmentation.
  • New stages are extending project duration as the economics shift. Energy capex has declined faster than power since 2022, while revenue uplift for four-hour BESS has grown.
  • The tradeoff between the revenue uplift, capex and connection/planning timelines drives the optimal strategy, including whether to augment or stage.
  • Projects avoid new grid connection applications for extensions by oversizing initial planning applications or adding only energy capacity.
  • Offline time/reduced availability for augmentation has been 1.1-1.3 months across Australian and international examples and just days for additional stages.

Lower cell costs and wider spreads favour extending energy capacity

Falling cell costs make extra hours cheaper relative to power-related infrastructure, altering the business case for changing sites. An owner who can reuse the connection, inverters, and other site equipment can avoid buying those components again.

Sign up to read this article for free

Unlimited access to our free articles

Monthly access to 2 Global Research articles

Benchmarks, Forecasts, Ko and more

Sign up for free

Already have an account? Log in

Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

Copyright© 2026 Modo Energy. All rights reserved