Data centres could contract 17% of renewable growth in the NEM by 2035 under draft regulations

Written by:

Data centres could contract 17% of renewable growth in the NEM by 2035 under draft regulations

Under draft federal and state regulations, data centres in the NEM could be required to bring their own renewable energy and support their round-the-clock load with firm contracts.

If data centres covered 90% of their load every hour with new supply in their own state, Modo Energy estimates they would favour 1.5x the wind capacity relative to solar in the lowest-cost generation mix. They would then firm that supply with a 2:1 split of 8-hour batteries and gas. Without gas, they would need three times the BESS capacity and would sell 75% of discharge to the grid.

We model regulations applying to sites switching on from 2028. This covers 1.7 GW of average data centre load, or 15 TWh. Reaching 90% firming coverage of that load would require 5.6 GW of wind and solar, 2.5 GW of batteries, and 1.3 GW of gas.

This makes data centres a major new source of long-term offtake in the NEM. This article covers what the proposed rules may require and the lowest-cost electricity and firming mix for each state to meet those requirements.

Executive summary

  • Governments want data centres to limit system impact by bringing new renewable energy and firm supply into their own state, so they don't raise prices for others.
  • Draft rules mandate firm contracts to cover load, risking fines or "turn-down" orders if demand isn’t met. Eight-hour batteries would do most firming, and gas would fill the hardest-to-reach gaps. Without gas, three times as many batteries would be needed.
  • Contracts could pay $35/MWh (42%) above the average spot price at 90% cover. This is assuming pricing that covers financing requirements, with surplus sold at the spot price.
  • Supply may need to be in the same state as the data centre. Victoria faces the tightest gap: its data centres would need about four-fifths of the state's forecast new wind.
  • Data centres could expedite grid connection if co-located with energy and storage, under a proposed companion AEMC request.

Data centre rules require firm contracts to cover load

On 20 October, the energy minister asked the AEMC to require firm contracts for data centres. The goal is reliability and price protection: a data centre should not add pressure to the existing system or raise consumer prices.

Large data centres would need to show the AER that firm generation, storage, or demand flexibility covers their load "appropriate to their demand shape and profile". The request suggests the AER could assess the full 24-hour profile and follow each site's ramp-up.

It also proposes that data centres source supply from new projects in their own state. Regulators are still designing these details.

Data centres would also need renewable generation matching

Both federal and state governments have taken the stance that new data centre demand should bring new renewable generation online, and not draw on existing supply. As part of that, the national AI standards would require sites over 30 MW to surrender one REGO for each MWh they consume.

In this analysis, we assume data centres would procure REGOs through PPAs as they also meet firming requirements.

​

New projects take years to build, so in the early years a share of certificates could come from existing wind and solar farms. The proposal is that this share falls each year until every certificate comes from a new project built for the obligation.

Eight-hour batteries would carry most of the firming, but gas covers the hardest-to-reach gaps

Modo Energy’s modelling estimates the lowest-cost contracted book for each state's covered data centre load in 2035. The rules catch only sites of 30 MW or more switching on from 2028, to reflect when policies may apply. This covers 15 TWh, about half of the 29 TWh data centres are forecast to draw in 2035.

To meet both energy procurement and firming, the model favours wind generation. Wind generation better matches the data centre’s round-the-clock load profile. This minimises excess contracted generation and can also sell back to the grid at higher capture prices. Still, solar is the cheapest way to meet midday demand, so 2.3 GW is built. To meet the firming parameters, solar and wind export 23% of their output in hours when the sites don't need it.

Eight-hour batteries then provide most of the firming, capped at 1.5 GW per GW of data centre load. At this cap, two-thirds of battery discharge goes to the grid rather than directly serving data centre load. More batteries selling surplus could be cheaper than gas. However, the cap limits the capital and market exposure to what a data centre would reasonably take on.

Gas then fills the hardest-to-reach gaps. In 2035, Victoria needs the most gas per GW of data centre load, followed by South Australia. This reflects the level of volatility in the region in 2035.

Without gas, firming would need about three times the batteries to reach the same coverage. In this scenario, the additional battery build uses solar more effectively and helps minimise exposure to wind droughts. So, in this scenario, solar builds 1.9x more, and wind reduces by 44% relative to the “with gas” scenario.

Full assumptions and sources are in our methodology.

Covering 90% of every hour would cost data centres about $35/MWh above spot prices

At 90% cover with gas, covered data centres would pay about $119/MWh in 2035 to cover capex and opex plus investors’ required return. This is $35/MWh above the $83/MWh average spot price in Modo's Central forecast. Still, this assumes they can re-sell excess at spot prices.

​

Without gas, they would pay about $2/MWh more, with re-selling. However, at three times the battery storage of the with-gas scenario, this re-sell is 75% of battery discharge and 36% of wind and solar output. This means data centres would sell the equivalent of 133% of their consumption to the grid, up from 64% with gas. If they could not sell surplus, the no-gas book would cost about $44/MWh more than the with-gas book on the same basis.

Victorian data centres contract most of the state's new wind

The 5.6 GW of contracted wind and solar equals about a sixth of the new generation Modo Energy forecasts will add to the NEM from 2028 to 2035, and almost a third of its new wind.

​

From 2028 to 2035, Modo forecasts 1.1 GW of new wind in Victoria. Victorian data centres would need 0.84 GW of wind, about four-fifths of that growth. Elsewhere, they would take about a quarter of new wind, a small share of new solar, and up to a sixth of new battery capacity.

Data centres could connect quicker if built with renewables and storage

To reduce the burden on transmission, a new AEMC rule change request proposes an integrated pathway for connection if co-located with generation and storage. This could enable more cost-effective, timely deployment of data centres alongside the procured generation mix. It would also incentivise hybrid deployment.

​

The connection application would be assessed on the facility's flexible operating profile rather than each asset's nameplate. The proposal also suggests staged connections, letting sites start within limits that rise as new supply arrives.

States are adding more specific regulations

The national rules set a floor, so states cannot compete for data centres by weakening them, though they can add stricter rules. Every state government except Queensland's accepts "new energy for new demand".

However, data centres buying from state-owned generators, which matters most in Queensland, could apply to the AER to modify their obligations.

​

Final criteria are still in design

The final regulations will confirm the parameters for energy procurement and firming. This includes defining the scope of firming, whether renewables must be procured in-state, and what qualifies as new generation.

Modo Energy can model your data centre energy costs

New NEM data centres are set to contract new wind, solar, and firming in their own state. Eight-hour batteries would do most of the firming, and gas would determine how much storage they buy. Each site's best portfolio depends on its state, load shape and the final rules.

Modo Energy can model data centre energy costs and optimise between on-site resources, contracted capacity, and merchant price exposure. It combines our NEM price forecast with a campus design, load profile, and network tariffs to find the lowest-cost way to supply a site. Contact the team to learn more.

Modo Energy (Benchmarking) Ltd. is registered in England and Wales and is authorised and regulated by the Financial Conduct Authority (Firm number 1042606) under Article 34 of the Regulation (EU) 2016/1011/EU) – Benchmarks Regulation (UK BMR).

Copyright© 2026 Modo Energy. All rights reserved